Springwell Village Residents Association
Filed under:
Meetings, Residents Meetings
Comments:
None
Residents Meeting
9th September 2025
Springwell Village Social Club
Present:
Angela Silk Chairperson
Liz Reid Vice-chairperson
Christine Brown Secretary
Mark Curry Treasurer
George Martin Committee Member
Pauline Cooper Committee Member
Alison Nairn Committee Member
Deborah Gallagher Committee Member
Keith Nairn Committee Member
In Attendance: Gareth Giles MMB Contracts Manager
Donna Rawlinson Northumbrian Water
Paul Wood Northumbrian Water Projects Manager
Amanda Hunt Northumbrian Water
Bethany Oakley MMB Customer Liaison
Apologies: Lesley Pickup Committee Member
Martin McKeever Committee Member
Dorothy Trueman Ward Councillor
Harry Trueman Ward Councillor
1. Minutes
The minutes of the previous meeting were proposed and seconded. Approved.
2. Update on Reservoir
Donna Rawlinson gave an update, starting with issues raised at the previous
meeting.
a) Why was the Project taking so long? Donna said that the work should be fully
completed by Spring 2026. Testing of systems continues. It took longer than
expected to fill the reservoir, partly due to the very hot dry summer.
b) Backfilling the site has commenced and should be done by the end of January.
The fencing should be installed by February. Landscaping is planned for February
and March. Cabins will be removed in April. Updates will be available on the
Northumbrian Water website portal.
c) Dust in the Village continues to be a problem. Northumbrian Water has asked
MMB to look for better ways to keep the dust down. This will be monitored but
the backfilling requires a lot of soil to be moved around which cannot be
avoided. The roadsweeper continues to be used.
d) Weeds have been removed from the bund as requested by residents and the
bund will be removed in December. Northumbrian Water continues to work with
Sunderland Council about the reinstatement of the roads upon completion.
e) A site visit had been arranged following the last meeting. About 20 residents
attended. They were shown what the fencing will look like and had discussions
about where it will be sited. They will write to residents when a decision has
been made. Planning permission will be needed for any changes.
f) The permanent road access to the site will have to be tarmac due to
maintenance needs.
A discussion ensued covering the following issues:
a) Weeds on the bund – They were removed but have now regrown and need
removing again.
b) Road surface – temporary repairs have been made but drivers are just using the
middle of the road due to the road surface crumbling at the edges. This is
dangerous.
c) Siting of fencing – residents noted there had been 2 proposals, at the top of the
site and half way up and wanted to know if a decision had been made about that
and also the height of the fencing. Was it going to be reduced to 1.8m or staying
at 2.4m? Donna said the fence would have to be 2.4m for security reasons.
Residents pointed out that this would look awful for the residents of Angel Rise
and they felt they were just being ignored. Paul Wood then informed the
Meeting that the fencing would be at the original position for operational
reasons. Residents asked if this meant the fencing would be higher than the
reservoir itself? Paul replied that communications about this would be
distributed soon.
d) The issue of roads in Eighton Banks by the Waggon Inn and Thomas Street was
raised, asking if they would be restored also. Paul replied that potholes would be
filled in but as it included private roads, permission to restore it was legally
complicated.
e) Residents said strongly that they felt they had been lied to by Northumbrian
Water from the beginning. The underground reservoir was not underground, it
would not protect the Green Belt as promised as the roof will be black granite
and the fencing will be very obvious even with shrubs. There had also been no
mentions of all the cabins and different sites around the Village during the
original consultations. It was noted that bedrock had been hit once the project
started which meant the reservoir was higher than intended. The bedrock issue
had been pointed out to Northumbrian Water in the very early consultation
stages by ex-workers at the local quarry but had been dismissed.
f) Residents asked about plans for bad weather for keeping roads clean and safe,
suggesting sandbags may be needed in heavy rain.
g) Landscaping plans were discussed noting that mature trees and shrubs were
needed both for the planned fencing and to replace the mature hedging that had
been removed. Donna said it was planned to be done in February and the plans
would be shared. It was pointed out by local gardening experts that it would be
better to plant in autumn so that they would benefit from autumn/winter/spring3
rain. It was also pointed out that maintenance – including watering particularly
when trees and shrubs were first planted – is very important. Paul said they
would not be using mature shrubs and trees as they were restricted as to what
could be bought. It was pointed out that mature trees and bushes can easily be
bought – they just cost more. Paul said landscaping plans were available but he
didn’t know which plants etc would be used. Donna offered to hold a
consultation session about this for residents to see the plans.
h) The colour of the access road was discussed. Residents felt strongly that there
were plenty of alternatives to black tarmac which could be used even if grassed
concrete was felt to be unsuitable. Residents also questioned why this plan had
changed to black tarmac at this late stage as Northumbrian Water must have
known what the weight requirements for the road were from the beginning of
the Project. The covering for the roof was also discussed. Residents had been
told a grass roof was suitable at the beginning then half way through told that
industry standards had been changed and black gravel was going to be used. It
was pointed out that other reservoirs and buildings have grassed roofs (the
example of a reservoir in Durham was cited as being entirely underground
within a very short distance of the city centre and other buildings) and also that it
was water companies – including NWL- who had decided on the industry
standard. Residents felt that decisions were being made purely on cost basis
regardless of the needs and wishes of the people who will have to live with the
reservoir for the next hundred years. And strongly felt they were not being given
the same consideration as an area such as Durham.
i) It was suggested that an early meeting should be held in 6 weeks to look at the
landscaping plans and that 3D models would be a great help. A vote was taken
and the proposal agreed – NWL agreed.
The Chairperson thanked Paul and his colleagues for attending.
3. Thompsons Quarry
Thompsons have sold the quarry to the Ashcourt Group based in Yorkshire. Ashcourt
Management at the Quarry no longer respond to contacts from the Residents
Association about operational matters apart from noting that monitoring will
continue as in the past.
Residents noted that had been an increase in activity at the site. Work now
commenced at 7am and often made tremendous noise moving things around the
site. Diggers and loud machinery can clearly be seen and heard working at 7am as far
away as Heugh Hill. Road conditions (dust etc) continue to be very bad, especially for
pedestrians.Residents were advised to send complaints including photo and video
evidence to the Environment Agency. Contact details will be put on the Residents
Association Facebook page. The Ashourt Group will be formally invited to the next
meeting.
4. Solar Farm
There is little to report. A Planning Inspector has still to be appointed and they will
have over 800 documents to read (over 500 from residents). Discussions had been
held with the Planning Inspectorate as they had allowed the appellants (Boom
Power) to add extra evidence after the deadline had closed but were told there had
just been a delay in entering them into the system.
5. Seldom Seen Park
A resident , Kevin Wright, approached the Council about the state of the Park. A
meeting was planned for Thursday the 11th September to discuss options, including
local volunteers resuming responsibility for some of the work. This had been the
original arrangement when the Park had been refurbished (2002 – 2005) under the
Doorstep Greens Project. It had proved difficult to get and keep volunteers, leaving
all of the work to 3-4 volunteers. Liz had spoken to Cllr Harry Trueman who said
there was still money in the Community Chest which could pay for equipment etc.
Kevin will keep the Residents Association informed of the outcome of the meeting.
6. Traffic.
It was agreed that traffic issues would be placed on the Agenda for the next
meeting.
7. Date of Next Meeting
This will be held in 6 weeks time.